As the TURBIX Energy team, we provide services with the experience we have gained in various critical projects in the energy production sector. The projects listed below are examples of the works in which our team members have actively participated and provided technical contributions in the past.
Esenyurt Combined Cycle Power Plant
Location: İstanbul, Türkiye
Scope of Work: 40 MW GE Frame 6001B, HGPI (Hot Gas Path Inspection)
At the scope of HGPI; following capital parts were replaced
First stage buckets, First stage shrouds, Second stage shrouds with honeycomb, Second stage buckets, Third stage buckets
Combustion system:
Combustion Liner, X-fire tubes, Bull Horns, Transition Pieces:, Primary Fuel Nozzle, Secondary Fuel Nozzles